Woodridge Elementary

Updated December 4, 2018

Woodridge Elementary
New Gym
Program/Design  January 2018 - February 2018
Construction Doc  March 2018 - July 2018
Bidding  August 2018 - September 2018
Construction  October 2018 - July 2019


New Fine Arts
Program/Design  January 2018 - February 2018
Construction Doc  March 2018 - July 2018
Bidding  August 2018 - September 2018
Construction  July 2019 -May 2020
 
Demolish Gym  June 2019
Renovate Classrooms  June 2020 - August 2020

Progress
December 2, 2018 - Foundation for the new gymnasium has been poured.  The storm drain piping is being installed.  Grading preparation for the ampitheater seating between existing gym and new gym is underway.  The gymansium's Pre-Engineered Metal Building Frame was delivered last week.
Image of Woodridge Elementary construction
Image of Woodridge Elementary construction      Image of Woodridge Elementary construction
October 29, 2018 - Construction fencing is in place and contractor mobilized.Upper-gradee playground equipment has been removed. Building pad preparation for the Gym is underway.
 Image of Woodridge Elementary construction Image of Woodridge Elementary Construction
 Image of Woodridge Elementary construction Image of Woodridge Elementary construction
September 28, 2018 - Pending board approval, construction on the Fine Arts Building and Gymnasium should commence October 8th.  Work will start with the Gymnasium and covered play area. 
Image of Woodridge rendering of Gym     Image of Woodridge covered play area
Click pictures to expand
 



AHISD welcomes patrons comments on any of the facility drawings.
Please email Mike Hagar at mikeh@ahisd.net

 

Website by SchoolMessenger Presence. © 2018 West Corporation. All rights reserved.