Facility Renovations

Updated November 13, 2019

Facility Renovations
Program/Design  November 2017 - February 2018
Construction Doc  March 2018 - May 2018
Bidding  June 2018 - July 2018
Construction  June 2019 - December 2019

 


November 13, 2019 - Walls are framed and sheathing is underway.  Power and plumbing are underway.
Junior School SST Kitchen  Junior School SST Kitchen
Junior School SST Sensory Room


AHISD welcomes patrons comments on any of the facility drawings.