Cambridge teachers, parents, and staff have been heavily involved in the design of the new playground. A community meeting was held the evening of Monday, October 23, 2018, to share information and gather input from the Cambridge community. The Cambridge playground and other campus upgrades have come before the AHISD Board of Trustees during several board meetings.
|
New Fine Arts
|
Program/Design |
August 2017 - October 2017 |
Construction Doc |
November 2017 - March 2018 |
Bidding |
April 2018 - May 2018 |
Construction |
June 2018 - April 2019 |
|
|
Install 4 Portables |
June 2018 |
New Playground |
May 2019 - August 2019 |
New Parking |
June 2019 - August 2019 |
|
|
Progress
|
September 30, 2019 - Community play area is complete. |
![Cambridge community play area is complete Cambridge community play area is complete](https://cdnsm5-ss9.sharpschool.com/UserFiles/Servers/Server_8062/Image/News%20images/Bond%20Updates/Cambridge/Cambridge%20ES%20-%20Ogden%20Play%20Area.JPG) |
August 29, 2019 - New play area and track are complete. New staff parking is open across Ogden. Community play area is slated to be complete in September. |
|
June 18, 2019 - Portables are gone and work has commenced for the new play area and playing field/track. |
![Cambridge Elementary has commenced on new play area Cambridge Elementary has commenced on new play area](https://cdnsm5-ss9.sharpschool.com/UserFiles/Servers/Server_8062/Image/News%20images/Bond%20Updates/Cambridge/Cambridge%20-%20Play%20Field.jpg) |
April 30, 2019 - The first grade class made the construction team a banner, gift bags, and cheered them on to the finish! The building is complete and teachers are moving in. Work continues on the landscaping in front of the new Fine Arts Building. Portable have been removed so work can commence on the new play area and playing field/track. |
![Orchestra Room at Cambridge Orchestra Room at Cambridge](https://cdnsm5-ss9.sharpschool.com/UserFiles/Servers/Server_8062/Image/News%20images/Bond%20Updates/Cambridge/3Cambridge%20-%20Orchestra%20Room.JPG)
![Planting beds Planting beds](https://cdnsm5-ss9.sharpschool.com/UserFiles/Servers/Server_8062/Image/News%20images/Bond%20Updates/Cambridge/6Cambridge_Planting%20Beds.JPG)
![Art Classroom Art Classroom](https://cdnsm5-ss9.sharpschool.com/UserFiles/Servers/Server_8062/Image/News%20images/Bond%20Updates/Cambridge/1Cambridge%20-%20Art%20Classroom.JPG)
|
March 22, 2019 - All exterior doors and windows have been installed. Concrete floors have been polished in Art Classrooms and corridors. Vinyl flooring and mirrors have been installed in Orchestra and Music Classrooms. Acoustical panels have been installed in all classrooms. Millwork has started to be installed in all spaces. Tile backsplashes and feature walls are in place. Ceiling-mounted power reels are installed in Art Classrooms. |
![Image of Cambridge Construction Image of Cambridge Construction](https://cdnsm5-ss9.sharpschool.com/UserFiles/Servers/Server_8062/Image/News%20images/Bond%20Updates/Cambridge/Cambridge%20-%20Art%20Classroom%20-%20Polished%20Concrete.JPG)
![Image of Cambridge Construction Image of Cambridge Construction](https://cdnsm5-ss9.sharpschool.com/UserFiles/Servers/Server_8062/Image/News%20images/Bond%20Updates/Cambridge/Cambridge%20-%20Music%20Classroom%20-%20Cabinetry.JPG)
![Image of Cambridge Construction Image of Cambridge Construction](https://cdnsm5-ss9.sharpschool.com/UserFiles/Servers/Server_8062/Image/News%20images/Bond%20Updates/Cambridge/Cambridge%20-%20Orchestra%20Classroom%20-%20Mirrors.JPG)
|
February 8, 2019 - ID'Hanis block feature wall has been installed. Dry wall and roof work continues. Roof top mechanical equipment has been set.
|
![Image of Roof Top Equipment Image of Roof Top Equipment](https://cdnsm5-ss9.sharpschool.com/UserFiles/Servers/Server_8062/Image/News%20images/Bond%20Updates/Cambridge/Cambridge%20-%20Roof%20Top%20Equipment.JPG)
![Image of D'Hanis feature wall Image of D'Hanis feature wall](https://cdnsm5-ss9.sharpschool.com/UserFiles/Servers/Server_8062/Image/News%20images/Bond%20Updates/Cambridge/Cambridge%20-%20D'Hanis%20Feature%20Wall.JPG)
|
January 9, 2019 -Installation of masonry and a new fire line is underway. Windows have been installed. Insulation and gypsum board are being installed in classroom spaces. |
![Image of Cambridge Fine Arts Entry Image of Cambridge Fine Arts Entry](http://www.ahisd.net/UserFiles/Servers/Server_8062/Image/News%20images/Bond%20Updates/Cambridge/Cambridge%20-%20Fine%20Arts%20Entry.JPG)
![Image of Cambridge Orchestra Classroom Image of Cambridge Orchestra Classroom](http://www.ahisd.net/UserFiles/Servers/Server_8062/Image/News%20images/Bond%20Updates/Cambridge/Cambridge%20-%20Orchestra%20Classroom.JPG)
|
December 2, 2018 - Roof work has commenced on the Fine Arts Building. Exterior waterproofing and insulation are being installed. Interior metal stud framing is underway. Scaffolding is erected and brickwork is scheduled to start soon. |
![Image of Cambridge Elementary construction Image of Cambridge Elementary construction](http://www.ahisd.net/UserFiles/Servers/Server_8062/Image/News%20images/Bond%20Updates/Cambridge/Cambridge%20Fine%20Arts%20Overall.JPG)
![Image of AHHS Commons Construction Image of AHHS Commons Construction](http://www.ahisd.net/UserFiles/Servers/Server_8062/Image/News%20images/Bond%20Updates/Cambridge/Cambridge%20Fine%20Arts%20-%20Masonry%20Mock%20%20Up.JPG)
|
December 2, 2018 - Canopy framing is underway. |
![Image of Cambridge Elementary Fine Arts Image of Cambridge Elementary Fine Arts](http://www.ahisd.net/UserFiles/Servers/Server_8062/Image/News%20images/Bond%20Updates/Cambridge/Cambridge%20Fine%20Arts%20-%20Canopy%202.JPG) |
October 29, 2018 - Steel framing and interior CMU wall construction have commenced. |
![Image of Cambridge Elementary construction Image of Cambridge Elementary construction](http://www.ahisd.net/UserFiles/Servers/Server_8062/Image/News%20images/Bond%20Updates/Cambridge/Wall1.png)
|
October 29, 2018 - Landscaping along Townsend and Cambridge Oval is complete. |
![Image of Cambridge Elementary Image of Cambridge Elementary](http://www.ahisd.net/UserFiles/Servers/Server_8062/Image/News%20images/Bond%20Updates/Cambridge/Cambridge%203.png)
|
September 29, 2018 - The concrete slab has been poured for the Fine Arts Building and steel will be erected in October 2018.
|
![Image of Cambridge Elementary concrete slab Image of Cambridge Elementary concrete slab](http://www.ahisd.net/UserFiles/Servers/Server_8062/Image/News%20images/Bond%20Updates/Cambridge/Cambridge%20-%20Fine%20Arts%20Classroom_Concrete%20Slab%201.JPG) ![Image of Cambridge Elementary concrete slab Image of Cambridge Elementary concrete slab](http://www.ahisd.net/UserFiles/Servers/Server_8062/Image/News%20images/Bond%20Updates/Cambridge/Cambridge%20-%20Fine%20Arts%20Classroom_Concrete%20Slab%202.JPG)
|
Click pictures to expand |
|
|
|
|
|
|
|
|
Cambridge teachers, parents, and staff have been heavily involved in the design of the new playground. A community meeting was held the evening of Monday, October 23, 2018, to share information and gather input from the Cambridge community. The Cambridge playground and other campus upgrades have come before the AHISD Board of Trustees during several board meetings.
AHISD welcomes patrons comments on any of the facility drawings.
Please email Mike Hagar at [email protected]