Natatorium (Excel Academy)

Updated March 31, 2020

Natatorium at Robbins
Natatorium
Construction          November 2019 - December 2020
 


 


March 31, 2020 - Concrete has been poured in the locker rooms and administration areas.  CMU is underway.  Foundation work for the spectator seating is ongoing.  Basement "lid" is being formed.
 Natatorium CMU Walls at Admin Area  Natatorium CPS Installing Gas Lines
Natatorium Elevated Slab at Bleachers  Natatorium Floor Protection for Polished Concrete
Natatorium Painting Structural Steel  Natatorium Preparing for Basement Lid Pour
February 18, 2020 - Pool excavation continues.  Basement walls are formed.
 Natatorium Basement Formwork  Natatorium Basement Formwork
Natatorium Pool Excavation
January 7, 2020 - Earthwork and pool excavation is underway.  
 AHHS Natatorium Earthwork  AHHS Natatorium Pool Excavation
Natatorium excavation
November 13, 2019 - Earthwork is underway.
Natatorium Earthwork
 


AHISD welcomes patrons comments on any of the facility drawings.